Grove Green Arch
VPMC worked with The Arch Company to remodel this fire damaged arch in line with the NWR Refurbishment Arch Guide in order to turn an unusable arch into to fully functional, dry and clean environment that Network Rail can lease out to Small local businesses.
The Arches are finished to a Basic Layout enabling the end user to modify the internal layout to their individual needs.
The arch barrel ceiling is lined with UPVC corrugated sheeting which follows the vaulted curved of the arch in order to direct any water seepage through the arch towards the perimeter ground drainage.
New incoming mains supplies and drainage were installed before the new power float floor slab was installed. The front and rear elevations had new part brick and glazed facades installed, as well as new internal electrics and an accessible W/C.