Asbestos Removal
Selson Road

VPMC provided a competitive quote to secure the contract to remove asbestos Insulation board from under the stair in this basement entrance.

 

Our team set up the decontamination unit before constructing a full enclosure around the effected area itself using 1000 gauge polythene. We connected a 2300 negative pressure unit to the enclosure with 3 x 750mm air lock. After the asbestos was removed the area was thoroughly cleaned, followed by a stage 4 air test. 

The client was issued with a waste note for the disposal and a clean air certificate upon completion.